Adelaide launches 11 housing projects starting early 2026

The Department for Housing and Urban Development timeline lists eleven projects across Adelaide with readiness dates through 2029, all requiring master planning before work begins.

By Adelaide News Desk · Published 20 July 2026

Listen in English · 2 min

How we reported this

This article was written by AI from the linked sources and was not reviewed by a journalist before publishing. The Daily Adelaide is part of The Daily Network and follows our reasonable editorial care.

Adelaide launches 11 housing projects starting early 2026
Photo by ozeraser / Flickr (CC BY 2.0)

Several Adelaide sites will reach housing construction readiness between February 2026 and December 2029 under the state government's published schedule. The Department for Housing and Urban Development timeline released this month lists eleven projects that together target thousands of new homes once master planning is complete.

2026 readiness dates

February 2026 marks the first listed date, with Noarlunga scheduled for 626 homes. Playford Alive eastern balance site follows in March 2026 for 1,480 homes, while the former West End Brewery site at Thebarton is listed for early 2026 and 1,000 homes. Greater Seaton Urban Renewal is set for July 2026 with 1,452 homes, and Smithfield reaches stage one readiness in November 2026 for more than 1,500 homes.

Elizabeth South on John Rice Avenue and Tapangka on Franklin Street both carry November and December 2026 dates. The latter project covers 329 homes plus mixed-use elements and is noted to run through 2030. Every entry on the timeline states that construction readiness remains subject to master planning.

Projects scheduled for 2027 to 2029

The Magill UniSA site is listed for 2027, with allotment numbers still to be confirmed after further discussions with Campbelltown City Council. Onkaparinga Heights, formerly known as Hackham, is scheduled for September 2027 and 2,000 homes. Concordia and Sellicks Beach appear at the end of the timeline for December 2029, carrying targets of 10,000 and 1,700 homes respectively.

The full list appears on the department's housing projects timeline page, which also directs readers to PlanSA's Land Supply Dashboard for an interactive regional view. No completion dates beyond the 2030 note for Tapangka are supplied for the other sites.

Next steps for each location hinge on completion of the required master planning processes. Prospective buyers, local councils and developers will track those approvals to determine when actual construction can start on the listed Adelaide sites.

References Sourced but Not Limited to:

Beta · AI-assisted · human oversight

Your newsroom. Shaped by you.

The Daily Adelaide is in beta. AI may assist with research, summarising and drafting. Automated checks assess sourcing, accuracy and editorial risk before publication, and sensitive material is held for human review. Spotted something off, or want us covering a topic? Tell us. Your feedback is entirely optional and helps shape what we publish next.